Legislation Details

File #: 24-22    Version: 1
Type: Action Item Status: Passed
In control: City Council
On agenda: 1/22/2024 Final action: 1/22/2024
Title: Setting a public hearing for the assessment of project costs for the conversion of the private Sleepy Hollow Phase I water system to the City's public water system. Ward(s): Ward 6 Councilor(s): Councilor Hoy Neighborhood(s): East Lancaster Neighborhood Association Result Area(s): Safe, Reliable and Efficient Infrastructure
Related files:

TO:                      Mayor and City Council   

THROUGH:                      Keith Stahley, City Manager   

FROM:                      Brian D. Martin, PE, Public Works Director

                                          

SUBJECT:

title

 

Setting a public hearing for the assessment of project costs for the conversion of the private Sleepy Hollow Phase I water system to the City’s public water system.

 

Ward(s): Ward 6

Councilor(s): Councilor Hoy

Neighborhood(s):  East Lancaster Neighborhood Association

Result Area(s): Safe, Reliable and Efficient Infrastructure

end

 

SUMMARY:

summary

 

The private water system supplying the residents of the Sleepy Hollow community had contained elevated levels of arsenic since at least 2012. Working with the homeowners, an agreement was reached with the City for the residents to be disconnected from the existing private Sleepy Hollow Phase I Water System and be connected to City water. In the agreement, a portion of the cost of the new infrastructure was to be paid by each property owner, who will be assessed under the procedures of Salem Revised Code (SRC) Chapter 21 (General Assessment Procedures). The assessment amount is $5,000 per property, which will go toward the total cost of the project. The project is now complete at a total project cost of $768,108.

end

 

ISSUE:

 

Shall the City Council schedule a public hearing for February 26, 2024, to receive public testimony concerning the assessment to property owners served by the Sleepy Hollow Phase I Water System?

 

 

RECOMMENDATION:

recommendation

 

Schedule a public hearing for February 26, 2024, to receive public testimony concerning the assessment to property owners served by the Sleepy Hollow Phase I Water System.

 

body

 

FACTS AND FINDINGS:

 

1.                     The Sleepy Hollow Phase I Water System had been operated as an independent small community water system within the jurisdictional boundary of Salem. The system served 114 residents through connections to 44 homes and a community center. The private system was supplied from a community well through a distribution system consisting of 4-inch and 2-inch PVC water lines.

 

2.                     Several tests conducted beginning in 2012 indicated the water delivered to Sleepy Hollow customers exceeded federal maximum contaminant levels for arsenic. In October 2019, Sleepy Hollow members voted to establish a new drinking water connection with City water and become water customers of the City of Salem. (Residents were already wastewater and stormwater customers of the City.)

 

3.                     In 2016, the City’s Water/Wastewater Task Force adopted a policy to subsidize the cost of connecting homes served by distressed private water systems and to assess those homeowners benefitting from the connection a maximum of $5,000 as a fair share of the project costs. The assessment is intended to be representative of the Water System Development Charge that is paid by a developer for a new connection to the water system with a residential property.

 

4.                     In March 2020, City Council authorized the improvement project for the Sleepy Hollow water system with the understanding that part of the cost of constructing the project would be assessed to owners of property benefitting by the improvements.

 

5.                     A majority of homeowners within the Sleepy Hollow Phase I Water System voted to pursue a connection to the City’s public water system, which is one of the requirements of SRC Chapter 21.

 

6.                     On October 25, 2021, and following a public hearing, City Council authorized staff to begin project activities to disconnect homeowners from the Sleepy Hollow Phase I Water System and connect the customers to the City’s water system. On this date, Council also established the assessment amount at $5,000 per property. (See File # 21-465.)

 

7.                     The City applied for and received a loan totaling $1,132,810 from the State of Oregon’s Safe Drinking Water Revolving Loan Fund for the construction of the project. Upon completion of the project, fifty percent of the loan amount became forgivable by the state. At a final project cost of $768,108 the forgivable portion totaled $414,054.

 

8.                     The 45 properties will contribute $5,000 each for a total of $225,000. The State of Oregon, through the forgivable portion of the loan, will contribute $414,054. The City will contribute the remaining $129,054 out of the Utility Fund.

 

9.                     In December 2023, a letter was mailed to all Sleepy Hollow property owners informing them of the completed project and of the intended assessment of $5,000 per property. In this letter, City staff committed to informing the property owners of the date and time of the public hearing during which Council would take action on the recommended assessment. Residents were also informed, subject to Council approving the assessment, that they would be afforded the option of either paying the assessment as a lump sum or having a lien placed on the property.

 

10.                     Staff are recommending a public hearing be scheduled for February 26, 2024, which will be followed by a first reading of Ordinance Bill No. 2-24 which will formally order the assessment.

 

 

BACKGROUND:

 

The Sleepy Hollow private water system had been experiencing elevated arsenic levels in water samples collected from the well since 2012. From 2012 to March 2020, 16 of 27 samples for arsenic exceeded the federal maximum contaminant level (MCL) for arsenic. In 2014, Sleepy Hollow entered into a Bilateral Compliance Agreement (BCA) with the Oregon Health Authority’s Drinking Water Services (DWS) to address the arsenic exceedances and to develop a plan to bring the system into compliance. However, the BCA was cancelled by DWS in February 2015 for inaction of the system overseers to pursue the steps outlined in the BCA. Another violation notice for arsenic was issued to Sleepy Hollow in July 2017.

 

At about this time, Sleepy Hollow approached the City on the possibility of converting their private system to City water. Representatives of Sleepy Hollow were presented with the options recommended and adopted by the Water/Wastewater Task Force in the 2016 white paper “Using Utility Funds to Subsidize Connecting Distressed Water Systems to City Water.”  Later, after conversations with the City, Sleepy Hollow members voted to continue the use of the current well and water system and develop a plan to abate the arsenic. Sleepy Hollow subsequently entered into another BCA with DWS to address the arsenic contamination.

 

As part of the new BCA, Sleepy Hollow contracted with HBH Consulting Engineers to conduct an evaluation of water supply and treatment options for the system. HBH presented three options: (1) connect to the City water systems and become customers of the City; (2) establish a bulk water connection with the City and become a wholesale customer; or (3) install a treatment system for arsenic and remain independent of the City. A majority of the members voted in October 2019 to pursue Option 1, connect to the public water system and become customers of the City. A formal request to connect was submitted to the City in March 2020. City Council approved the construction project in 2020 and approved an assessment of benefit properties in 2021. The project was completed in 2023.

 

 

                     Robert Chandler, PhD, PE    

                     Assistant Public Works Director

 